Contractors for Barratt Homes are intending to close parts of Brentfore Street for up to three days during the week starting Monday 4th September. The closures will affect the junctions of Brentfore Street with Holne Road and with Timoney Place. The closures are to allow the junctions to be resurfaced. Access to the section of
In a letter sent to local councillors but not yet to East Wichel residents, Brian Peers, the Adoptions Manager at Taylor Wimpey, says that they will be starting work, again, preparing the roads in East Wichel for adoption. Taylor Wimpey have started work on East Wichel’s roads many times before and never seem to get
It’s over six months since Barratt Homes announced that road surfacing would take up to two months and be complete by mid-March. Now, after several delays including a change of contractor and a dispute with Swindon Borough Council, the end is finally in sight for their work. A letter to residents of Holne Road, Rylane,
Bloor Homes are surfacing Stonehenge Road between the junctions with Trevello Road / Aviemore Road and Staldon Road / Ravensdale. Their works will take four weeks and are already into their second week. Persimmon are surfacing Trecastle Road and Dunsley Vale, and expect their works to take just three days this week. Let’s hope they’ve
Barratt Homes have written to residents in East Wichel, explaining the latest delay to surfacing work on Holne Road and Brentfore Street. The final surfacing and completion of our current works on site has been delayed due to a detailing issue raised by Swindon Borough Council which is applicable to all developers on the Wichelstowe
Barratt Homes have set dates for surfacing the four roads in the part of East Wichel they developed. Rylane and Holne Road will be surfaced on 12 February, whilst Timoney Place and part of Brentfore Street will be surfaced on 18 March. Repairs to the roads, paths and kerbs will start up to a month